Corbii Mari172 MW

Dâmbovița County, Romania2026In progress

172 MWbuilt by our team
130,200piles in our scope
338,520modules in our scope
6,714tables 2V26 + 2V13
2,441 kmDC solar cable (plot 4)
up to 155people on site at peak

About the project

Mechanical and electrical works on 172 MW of a fixed-tilt park. Pile driving went on through the winter. All figures below come from the daily site reports and the park layout.

Works carried out

  • Setting out and pile driving
  • Mounting structures
  • Module installation
  • DC/AC cabling
  • Connections and commissioning

Project carried out by the SMACO team while working for a previous company.

Best day on site

1,016piles driven
5,732modules mounted
117tables assembled
102.7 kmDC cable laid

From the site

Tap a photo to see it larger.

Corbii MariCorbii MariCorbii MariCorbii Mari

Have a park to build? Send us the layout and the deadline.